Notice: wpdb::prepare was called incorrectly. The query does not contain the correct number of placeholders (2) for the number of arguments passed (3). Please see Debugging in WordPress for more information. (This message was added in version 4.8.3.) in /home/werk/public_html/wp-includes/functions.php on line 4100
Vox Technology Park site during May 2017 - Werk MB Construct

Vox Technology Park site during May 2017

Back to articles

This month, concrete was poured over the 10th floor in building A and over the 7th floor in building B, finishing the last floors of Vox Technology Park.

The steel frame was mounted over the exterior of the sixth, seventh and eighth floors, then the windows and curtain walls were mounted. Plumbing was completed from the basement up to the third floor.

The plumbing was installed for the first, second and third floor, as well as for the basement. Work began on plasterboard, while the masonry work was completed for the fourth and fifth floors.

The good weather continues, allowing us to progress at a steady pace, so the building is taking shape nicely. Stay tuned for the next instalment of works progress at Vox Technology Park!

Source: Vox Technology Park